Key Metrics
Cost Range:  $10-$20 Million / Mile (parallel track)
4800 tons of steel / mile (rail only)
85,000 square feet of PV / mile
~ 1 Megawatt / mile / solar-hour
~ 238 cubic meters of hydrogen / mile / hour
~ 30 gallons of water / mile / hour (purification)
Self sustaining 3-100 Transports Per Mile 24/7/365 (variable mass)
Standard Installation includes:
3 Transports / 1 mile
2 Traveler Stations / 5 miles
1 ITC Utility Substation / 3 Miles
The Hydrogen Superhighway